East Herts Surfacing Services

Delivering expert tarmac, resin, and block paving solutions across East Herts and beyond.

/
/
/
/
/
/
/
/
/
East Herts Surfacing Bitelli paver laying tarmac at St Catherine’s School

Machine-Laid Surfacing & 10mm SMA

St Catherine’s School, Hoddesdon – Project Update 3

The surfacing stage is now well under way at St Catherine’s School in Hoddesdon, our major groundworks and surfacing project for Hertfordshire Council under a contract worth over £500,000.

After the excavation in Update 1 and the groundworks and first roadway in Update 2, the team has moved onto the finished surfaces. The new playground beside the school buildings has been machine laid and rolled, and the latest areas are being surfaced in a 10mm SMA (stone mastic asphalt) surface course.

This update follows the full process step by step, with photos and video straight from site.

ClientHertfordshire Council
Contract valueOver £500,000
LocationSt Catherine’s School, Hoddesdon
Surface course10mm SMA
LayingBitelli BB650 paver
CompactionHamm twin-drum rollers

Our Surfacing Process

Every area at St Catherine’s goes through the same five stages, so each new section matches the last and the whole site finishes to one consistent standard.

  1. Prepared baseExcavated, levelled and compacted ground ready to take the new surface.
  2. Machine layingHot SMA fed through the paver and laid at an even depth and level.
  3. RollingTwin-drum rollers compact the mat while it’s still hot.
  4. Joints & edgesRaking, luting and plate compaction for tight joints and clean edges.
  5. Finished surfaceA smooth, dense, hard-wearing surface ready for daily use.

Why 10mm SMA?

SMA (stone mastic asphalt) is a premium surfacing material made up of a high proportion of strong, interlocking stone held together by a rich bitumen mastic. That stone-on-stone structure is what makes it so tough and long lasting.

The 10mm refers to the maximum stone size. It gives a tight, fine-textured finish that looks neat, is comfortable underfoot and stands up well to the constant footfall and vehicle traffic a busy school site sees every day.

10mm SMA stone mastic asphalt ready to lay at St Catherine’s School, Hoddesdon
The close-up above shows the 10mm SMA ready to lay: dense, evenly coated stone that knits together into a smooth, durable surface once it’s rolled.

Machine Laying for a Smooth Finish

Laying by machine is the key to a smooth, level surface across a large area. Our Bitelli BB650 paver takes the hot SMA into its hopper, spreads it evenly across the width of the run and lays it through the screed at a consistent depth.

The crew walk alongside the paver the whole time, keeping an eye on the levels, the edges and the material feeding through, so the finish stays the same from one end of the run to the other.

VideoMachine laying the SMA for a smooth, even finish
VideoHopper loaded with SMA, with the roller following close behind
VideoPaver and crew working the next run

Rolling and Compaction

Compaction is where the strength of the surface is made. Straight behind the paver, our Hamm twin-drum rollers work the fresh mat while it’s still hot, pass after pass, locking the stone together into a dense, durable layer.

Timing matters here. Rolling at the right temperature gives a tight, closed surface with no loose stone, which is exactly what you want on a school playground and roadway.

VideoRolling the new SMA surface
VideoFinal roller passes along the edge

Joints, Edges and Hand Finishing

The machine does the big areas, but a quality finish comes down to the detail. Our team rakes and lutes every joint so new and existing runs meet flush, then uses a plate compactor along the edges and in tight spots the roller can’t reach.

Corners, kerb lines and the areas around buildings and fences are all finished by hand, so the surface stays neat and even right up to the edge.

Raking the joint ahead of the roller on new SMA surfacing
Paver and hand work in the corner of the school yard

The New Playground 6mm SMA

The new playground alongside the main school building has been machine laid and rolled. Even on a grey, wet day the crew kept the paver and rollers moving, laying long, straight runs right up to the building line.

The photos show the new surface taking shape against the old one, and how clean the finished joint lines and edges are.

VideoPaver laying the new playground beside the school
VideoWalk-through of the new playground
VideoLaying progress alongside the building
VideoThe joint line on the new surface
VideoThe finished playground

The Finished Surface

Once it’s rolled and cooled, the result is a smooth, even surface with a tight, uniform texture. The close-ups show just how consistent the finish is across the whole area, with no loose stone, no ridges and clean, straight edges.

It’s a surface built to cope with years of school life: playtimes, PE, deliveries and daily drop-offs.

Project Update

With the playground surfaced and the SMA going down across the latest areas, St Catherine’s is really starting to come together. Work continues on the remaining playgrounds, pedestrian footpaths and roadways.

Catch up on the project so far: Update 1 – excavation and ground preparation and Update 2 – groundworks and the first roadway.

Next: Update 4 – the main entrance and access road, planed off and machine laid in 10mm SMA.

We’ll keep sharing photos and updates as the work progresses.

Gallery

Every photo from this stage of the work at St Catherine’s School, Hoddesdon, from machine laying and rolling to the finished 10mm SMA surface.

Let us help you get your project started.

Contact us