Line Marking the New Entrance, Car Park & Access Road
St Catherine’s School, Hoddesdon – Project Update 5
Update 5 from St Catherine’s School in Hoddesdon, our major groundworks and surfacing project for Hertfordshire Council under a contract worth over £500,000.
In Update 4 the main entrance and access road were planed off and machine laid in 10mm SMA. With the new surface down, the next job was the one that makes it all work: line marking. Double yellow lines now run the length of the entrance road and around the turning area, white arrows direct the flow of traffic, and the car park has fresh bay lines and hatched keep-clear areas.
Here’s a look at the finished markings on a crisp autumn morning.
What Went Down
Four types of marking, each doing a specific job around a busy school entrance.
- Double yellow linesNo waiting at any time along the entrance road and around the turning area, keeping the approach to the gates clear.
- Direction arrowsClear one-way guidance so traffic flows the right way through the entrance and access road.
- Parking baysCrisp white bay lines laid out on the new car park surface.
- Hatched markingsKeep-clear areas that stop vehicles stopping where they shouldn’t.
Keeping the Gates Clear
The school gates are the pinch point of the whole site: parents, staff, deliveries and minibuses all meet here at the same times every day. The new double yellows follow the kerb line right around the entrance and turning area, so the approach to the gates stays clear and sightlines are kept open.
Against the fresh black SMA, the yellow lines and white arrows stand out exactly as they should.
Arrows and Bays
Direction arrows on the access road guide traffic one way through the site, while the car park has been set out with clean white bays and hatched areas to keep the pedestrian routes free of parked cars.
How We Mark a New Surface
Marking goes on once the surface has fully cooled and been swept, and every line is set out before it’s applied.
- Surface readyThe new 10mm SMA from Update 4 has been rolled, cooled and swept clean.
- Set outEvery line, arrow and bay is measured and chalked out first so the layout is right before any paint goes down.
- MarkLines applied in sharp, consistent widths, with clean edges and tight curves around the kerbs.
Project Update
With the entrance, access road and car park surfaced and marked, the front of St Catherine’s is complete and back in use. Work continues across the remaining areas of the site.
Catch up on the whole project so far:
We’ll keep sharing photos and updates as the work progresses.