East Herts Surfacing’s Bitelli BB650 paver laying 10mm SMA at the main entrance of St Catherine’s School

Main Entrance & Access Road Resurfacing

St Catherine’s School, Hoddesdon – Project Update 4

Update 4 from St Catherine’s School in Hoddesdon, our major groundworks and surfacing project for Hertfordshire Council under a contract worth over £500,000.

With the playground surfaced in Update 3, the team has moved to the front of the site: the main entrance and access road, the first thing every pupil, parent and delivery driver sees. The old surface has been planed off and replaced with a machine-laid 10mm SMA surface course, part of circa 4,000 m² of SMA going down across the site.

This update follows the entrance road from planed base to finished surface, with photos and video straight from site.

ClientHertfordshire Council
Contract valueOver £500,000
LocationSt Catherine’s School, Hoddesdon
This updateMain entrance & access road
Surface course10mm SMA, machine laid
PlantBitelli BB650 paver, Hamm rollers

Planed Off and Ready

Before any new material went down, the existing entrance surface was planed away. Planing removes the old, worn layer and leaves a level, textured base that the fresh SMA bonds to, so the new surface sits flush with the kerbs and drainage rather than on top of the old road.

You can see that keyed base in the photos below, with the Bitelli BB650 paver already in position to start the first run.

New SMA going down over the planed surface, roller and crew at work

Four Stages to a New Entrance

The same sequence that delivered the playground in Update 3, applied to the busiest piece of ground on the site.

  1. Plane offThe old, worn surface is planed away to a level, keyed base.
  2. PrepareThe base is swept clean and levels checked against the kerb line.
  3. Machine layHot 10mm SMA goes down through the Bitelli BB650 at an even depth.
  4. Roll & finishTwin-drum rollers compact the mat while edges and joints are finished by hand.

Machine Laying the Entrance Road

With the base ready, the Bitelli BB650 took over. Hot 10mm SMA is tipped into the hopper, spread across the full width of the run and laid through the screed at a consistent depth, with the crew walking the edges to keep the levels and lines true.

Laying by machine means the whole entrance went down in long, continuous runs rather than in patches, which is exactly what gives a surface this size its smooth, even finish.

VideoThe Bitelli BB650 laying 10mm SMA on the entrance road
Long run of new SMA with the paver and tipper at the far end
The entrance takes more traffic than anywhere else on the site: cars, minibuses, deliveries and hundreds of pedestrians every school day. A machine-laid 10mm SMA surface gives it the smooth, dense finish it needs to stand up to all of it.

Rolling Behind the Paver

Straight behind the paver, our Hamm twin-drum rollers work the fresh mat while it’s still steaming hot, pass after pass, locking the stone together into a dense, closed surface. The crew rake and lute the joints and edges ahead of the roller so every run meets the last one flush.

Timing is everything here: roll it at the right temperature and you get a tight, uniform surface with no loose stone and no ridges.

VideoRolling the new SMA while the crew rake and lute the edges

Tight to the Kerb

An entrance is judged at its edges. The new SMA has been laid and compacted hard up against the kerb line, so there are no gaps for water to sit in and no loose edge to break away under turning traffic.

The Finished Entrance

Rolled, finished and cooling: the new entrance and turning area outside the school buildings, with clean kerb lines and a smooth, consistent surface from the gates to the main road. The plate compactor takes care of the final edges and corners the roller can’t reach.

It’s a surface built for years of daily drop-offs, deliveries and school traffic.

Completed main entrance surfacing at St Catherine’s School, Hoddesdon

Project Update

With the main entrance and access road surfaced, another big piece of St Catherine’s is complete. Work continues across the remaining areas of the site.

Catch up on the whole project so far:

Next: Update 5 – line marking the new entrance, car park and access road.

We’ll keep sharing photos and updates as the work progresses.